Your cost to build

Change anything and the budget, savings, schedule and loan draws update instantly.

Square footage
Market & finishes
What you'll do yourself

Planning-grade estimates based on national averages. Get real bids before you lock a loan amount.

All-in cost
$700k
land + build
Build cost
$550k
$256 per finished sf
You save
$55k
vs. hiring a builder
Timeline
39 wks
about 9 months

Totals include site work, permits, well and septic, and a 10% contingency, not just the house itself.

Where the money goes
Site & structure 30%Envelope 16%Systems 16%Interior 22%Soft costs 17%
Line-item budget
DivItemCost
Site & structure
02Site prep & excavation$22,937
03Foundation & flatwork$50,461
06Framing materials & sheathing$59,636
06Framing labor$32,112
Envelope
07Roofing$22,937
08Windows & exterior doors$22,937
07Siding, stone & exterior trim$27,524
07Insulation$13,762
Systems
22Plumbing$32,112
23HVAC$27,524
26Electrical$27,524
Interior
09Drywall$22,937
12Cabinets & countertops$27,524
09Flooring & tile$22,937
06Interior doors & trim$18,350
09Paint$13,762
11Fixtures & appliances$13,762
Soft costs
01Permits & impact fees$13,587
01Engineering & plan changes$4,500
01Builder's risk insurance$2,294
33Well, septic & utility hookups$25,000
01Contingency (10%)$45,874
Total build cost$549,992

Build schedule

Phases in order. DIY phases run longer because they happen on evenings and weekends.

Permits & plans
6 wk
Site & excavation
2 wk
Foundation
4 wk
Framing
6 wk
Roof & windows
3 wk
Rough-ins
4 wk
Insulation
1 wk
Drywall
4 wk
Cabinets & trim
4 wk
Flooring & paint
3 wk
Finals & occupancy
2 wk
SubcontractorYou

Subs to line up

Get at least three bids for each. Dashed trades are ones you're doing yourself.

  • Excavator
  • Foundation / concrete
  • Lumber yard
  • Framer
  • Roofer
  • Window supplier
  • Siding / mason
  • Insulation
  • Plumber
  • HVAC
  • Electrician
  • Drywall tape & finish
  • Cabinet / counter shop
  • Flooring / tile
  • Finish carpenter
  • Painter
  • Appliance supplier

Construction loan draws

A typical five-draw schedule. Your lender's may differ.

Draw 1 · 15%
$82,499

Foundation: Footings, walls and slab poured and inspected

Draw 2 · 30%
$164,998

Dry-in: Framed, roofed, windows in

Draw 3 · 20%
$109,998

Rough-ins: Rough-ins and insulation pass inspection

Draw 4 · 20%
$109,998

Drywall & trim: Walls finished, cabinets set

Draw 5 · 15%
$82,499

Final: Certificate of occupancy issued

Save this estimate.Create a free account to keep it as a project. Tracking spending, bids and draws against it is coming soon.